Public Works

Update: Water Supply Status (Day 8)

Release Date: 
08/14/2017

Water supply work began this morning at Well 2 located in Roy Raley Park. Well 2 is the city’s largest production well at about 2.6 million gallons per day.

Update: Well 5 Back Online

Release Date: 
08/12/2017
As of now, one of two city wells was brought back online. Water supply and customer demand have been balanced at about 5.5 million gallons per day with the voluntary curtailment.

Update: Water Supply Status

Release Date: 
08/11/2017

Water supply is still being maintained at about 5.5 million gallons per day with voluntary curtailment.  Pendleton water customer’s efforts continue to be appreciated.

 

Update: Water Supply Status

Release Date: 
08/10/2017

Water supply is still being maintained at about 5.5 million gallons per day with voluntary curtailment with adequate water levels in the water system.  Peak demand with irrigation is typically about 10.5 million gallons per day.  Pendleton water customer’s efforts have been greatly appreciated.

 

Update: Water Supply Status

Release Date: 
08/08/2017

Water supply was checked at 4 am this morning. Nighttime water level recovery in the water system was very similar to what was seen before the first well, Well 5 (Stillman), went off-line last week. This is good news. It means the voluntary effort in minimizing outdoor watering is working at this time. City staff will continue to monitor the situation and provide brief updates. 

 

Public Notice - Voluntary Water Conservation

Release Date: 
08/07/2017

City of Pendleton has its two largest water supply wells out of service as of early this morning.  These two water supply wells provide about 4.6 million gallons of water per day.  Our summer peak demand due to outside irrigation is about 10.5 million gallons per day and non-irrigation season demand is about 2.2 million gallons per day.  City is asking all water customers to voluntarily curtail their outdoor water usage as much as possible until further notice. 

SE 8th Street Bridge Open House Presentation

Release Date: 
08/02/2017

In providing this presentation, the city, state, and consultant reviewed the project schedule, reuse of the bridge trusses, project design, roadway sections, temporary work bridge and in-water work window, and the next steps: executing construction contract Fall 2017, starting construction Spring 2018, and completing the overall project Fall 2019.  The river crossing is expected to be unavailable for about 10 months, with north side residents using an alternative route during this period.  The new bridge is expected to be open to the public in Spring 2019 with removal of the tempo

SE 8th Street Bridge Open House Announcement

Release Date: 
07/12/2017

The Knights of Pythias will be hosting a BBQ and open house at their lodge on Monday evening, July 31, 2017.  The BBQ will start at 6 pm and the open house presentation will start at 7 pm.  Based on the progress of their project we will likely have the BBQ in an outdoor setting, and the presentation will take place inside their lodge.

Air Quality Commission

Release Date: 
02/16/2017

There will be an Air Quality Commission meeting this evening at 6:00 pm in the Community Room located at the back of City Hall.  

CANCELLED; Air Quality Commission Meeting

Release Date: 
01/19/2017

The Air Quality Commission has canceled its meeting tonight which was scheduled in the Community Room from 6:00-8:00 pm.

The next scheduled meeting will be on Thursday, February 16, in the Community Room from 6:00-8:00 pm.